The NSW Government has implemented a package of changes around the protection of trees and other vegetation in urban areas. The reforms toughen-up the legal regime. It will make things more difficult for people who have carried out unauthorised tree (or vegetation) pruning, lopping or removal in non-rural settings.
On Friday 23 October 2026, the Government published the Environmental Planning and Assessment Amendment (Vegetation) Regulation 2026. The regulation had immediate effect.
The regulation was accompanied by the State Environmental Planning Policy Amendment (Vegetation) 2026. This document made amendments to several state environmental planning policies. It also had immediate effect.
This article is of a general nature only and is not a replacement for legal advice. It does not deal with all of the changes that have been made by the NSW Government. It summarises some key changes from the perspective of private landowners and property developers.
At present, local councils and the Planning Secretary can issue development control orders to deal with a wide range of potentially unlawful activities. They are a common first response when a local council perceives there to be a compliance problem.
A person who receives such an order must comply with it. However, they have a right to appeal to the Land and Environment Court within 28 days of receiving it and could, once the matter is appealed, apply for a ‘stay’ (suspension) of the order.
The development control order regime is long-standing. In particular, it enables orders to be made to stop the carrying out of unauthorised building work or subdivision work.
However, there has been a loophole in the regime — in that vegetation clearing or removal that was not for the purpose of the erection of a building or a subdivision was potentially not able to be the subject of a development control order.
While the Department of Climate Change, Energy, the Environment and Water (DCCEEW) has power to issue stop work and remediation orders for unauthorised native vegetation clearing under the Biodiversity Conservation Act 2016, local councils have lacked similar powers. This is particularly relevant in an urban context where DCCEEW does not necessarily have a strong interest.
The NSW Government have now moved to address this.
The new regulation has created a new type of development control order under the Environmental Planning and Assessment Act 1979 (the EP&A Act).
This is called a ‘Vegetation Order’. It can be issued by a local council when vegetation is ‘cleared’ in contravention of the EP&A Act.
The order can require a property owner or developer to stop ‘clearing’ vegetation and/or to carry out remediation work to replace cleared vegetation. The vegetation concerned could be native or exotic vegetation. This enables a local council to take action, for example, when exotic vegetation is cleared when the vegetation has no biodiversity value (but, for example, may have amenity value).
The word ‘vegetation’ is defined to mean a tree or other plant.
The words ‘clearing’ and ‘cleared’ are given a special legal definition. A person is said to have ‘cleared’ vegetation if, among other things, they cut down, fell, uproot, kill, poison, ringbark, burn or otherwise destroy the vegetation. They are also regarded as ‘clearing’ vegetation if they lop or otherwise remove a substantial part of the vegetation.
Where vegetation has been planted as a consequence of a development control order it cannot be later cleared without a development consent or permit from the local council. This applies even if the vegetation is of a kind that ordinarily would not require a permit to remove (under the relevant development control plan).
There is now a new regulatory provision preventing a certifier from issuing a complying development certificate when the certifier knows — or ‘ought reasonably to know’ — that vegetation on the land was cleared in contravention of the State Environmental Planning Policy (Biodiversity and Conservation) 2021. In brief terms, this is a reference to clearing that took place in a non-rural area without either a required development consent, a tree permit issued by a local council or an approval granted by the Native Vegetation Panel.
The new provision does not apply if the unauthorised clearing is more than five years old. It also does not apply if a development control order was issued in relation to the clearing and the conditions of that order have been satisfied.
This new provision operates not just when a certifier actually knows about unauthorised clearing, but when the certifier ‘ought reasonably to know’ about the clearing.
In relation to this latter requirement, in our view:
There is now a new regulatory provision preventing a certifier from issuing a complying development certificate for development involving the clearing of:
There is now a new regulatory provision that will apply to complying development certificates for development that involves building work or subdivision work on land:
When this occurs the complying development certificate must be issued subject to the condition replacement vegetation is retained and maintained on the land.
There are now new on-the-spot fines for the unauthorised clearing of vegetation in non-rural areas.
The previous on-the-spot fine was (generally speaking) $3,000 for individuals and $6,000 for corporations.
There are now new, higher, on-the-spot fines of:
(the higher fines applying to a more serious category of breaches).
The process of issuing permits by local councils will now be more legalistic and process-driven.
A new rule has been introduced that a council must not issue a tee/vegetation permit unless the council has considered the following:
This means that, if councils want to minimise the risk of legal challenges to the permits they issue, they are likely to
In a related-measure the NSW Government has introduced Environmental Planning and Assessment Amendment (Vegetation) Bill 2026 into the state parliament.
The proposed law would introduce a civil penalties framework for illegal vegetation clearing into the EP&A Act.
Under the current law if a person unlawfully clears vegetation they can either be issued with an on-the-spot fine (a ‘penalty notice’) by the local council or they can be prosecuted for a criminal offence. There is currently nothing in between those two actions.
The proposed law will give councils a further option.
The Planning Minister, Paul Scully, says that this option might be appropriate, for example, for more severe instances of illegal clearing, like the poisoning and felling of 265 trees at Castle Cove in 2023.
A local council will be able to commence ‘class 4’ proceedings in the Land and Environment Court. These will be civil proceedings, rather than criminal proceedings. A fine will be able to be imposed by the Court. The maximum civil penalties will be set at half the maximum criminal penalties—that is, $500,000 for an individual and $2.5 million for a corporation.
Significantly, the Court can impose these fines based on a civil, rather than criminal standard of proof.
In civil proceedings, factual matters are determined based on the balance of probabilities. That is, it must be more likely than not that a contravention occurred. In criminal proceedings a person must be proven to be guilty beyond a reasonable doubt. Under the current law, large fines could only be imposed when the criminal standard of proof is met.
From time-to-time landowners are accused by local councils of unlawfully destroying trees on their properties, when the properties are largely untended (because they are, for example, future development sites). Often the council may find that it cannot prosecute the landholder because:
Under these new provisions, if passed into law by the parliament, local councils may try their luck with this new option, and pursue the imposition of a civil penalty in the Land and Environment Court.