By Anthony Whealy, Partner and James Oldknow, Associate
Once again, planning legislation probably needs to be quickly amended to sensibly deal with the implications of this latest decision.
In our July article ‘Update: Calculating Gross Floor Area (for FSR purposes) in NSW (July 20-21)’ we had reported on a Land and Environment Court decision in Buyozo Pty Limited v Ku-ring-gai Council [2021] NSWLEC 2, where the Court had held (in an appeal relating to a modification application seeking to modify a condition of development consent to reduce the amount of development contributions already paid) that the corridors leading from a carpark to the entrance of individual storage units within a self-storage facility were excluded from the calculation of GFA (at [32]) on the basis that those areas fell within the ‘loading or unloading of goods’ exclusion at (h) of the Standard Instrument definition of GFA.
The practical result of that exclusion of GFA was that the applicant had overpaid approx. $300,000 in development contributions required by s.7.11(1) of the Environment Planning and Assessment Act 1979 (EPA Act) because the relevant Contributions Plan provided an applicable rate per square metre of GFA.
However, that outcome was short-lived as the earlier reported findings have very recently been overturned by the NSW Court of Appeal in Ku-ring-gai Council v Buyozo Pty Ltd [2021] NSWCA 177, a Judgment handed down on 13 August 2021.
There are 2 important observations arising out of the Court of Appeal Judgment, which relate to:
In relation to the first point, the Court of Appeal held that the primary Judge had erred in interpreting the definition of GFA because:
In relation to the second point, relating to the power to modify a development consent generally, the Court of Appeal held (somewhat breathtakingly) that there is no power to modify a development consent to amend a condition of consent requiring a monetary contribution, at least in isolation, because:
This is a highly surprising decision which does not sit comfortably with decades of case law (in both the specialised Land and Environment Court, and the Court of Appeal itself) and goes directly against industry practice, by which developer contributions are frequently sought to be altered by way of modification application. The Court of Appeal decision holds that there is simply no power to modify developer contribution conditions, at least without the development itself being modified.
Importantly though, not all avenues to amend conditions of development consent requiring the payment of monetary contributions are lost because Preston CJ reminded the industry of the 3 (current) solutions to this issue (at [66]-[70]), including:
Unfortunately, the practical outcome of this part of the Court of Appeal’s decision is that developers in NSW will now be pushed towards the 2nd solution above (direct appeals to the Land and Environment Court) to contest unsatisfactory conditions of consent that do not effect a change to the approved building and/or its use, such as those which relate to the payment of monetary contributions. That is, in these circumstances lodging a s4.55 modification application with the Council (or a s.4.56 modification direct to the Court) is simply no longer an option at all.
With the above in mind, it is important to remind our readers that:
Ultimately, it seems to us that if a developer were to seek changes to an approved building and/or its use in addition to seeking to amend a condition of consent requiring the payment of a monetary contribution, and there was some nexus between those changes, this could be sought via a modification application. This is of course an untested point given it has only been 1 week since the Court of Appeals decision. However, we expect this question will be tested in the very near future because it seems that this would overcome the Court of Appeal’s very technical observation that a mere challenge to conditions does not “engage” the modification power. A change to the building(s) (i.e. the approved DA drawings) would certainly then ‘engage’ the modification power.
As always, if you need further assistance or advice dealing with these issues, we are ready and able to assist.
If you would like further information or have any queries regarding other matters, please do not hesitate to contact: