By Stephen Aroney, Partner and Leon Chen, Associate
In 374, 376 New South Head Road Pty Ltd v SMLXL Projects (NSW) Pty Ltd [2025] NSWSC 886, William J held that 374, 376 New South Head Road Pty Ltd (the Developer) failed to establish an arguable case that its claims against SMLXL Projects (NSW) Pty Ltd (the Contractor) (who had been placed into liquidation less than a week after the expiration of its insurance policy) would have been indemnified by its professional indemnity insurance Insurer. This decision highlights the strict hurdles facing third party claims under the Civil Liability (Third Party Claims Against Insurers) Act 2017 (NSW) (TPC Act).
On 23 December 2020, the Proprietor entered into a design and construct contract with the Contractor to carry out certain design and construction works at 374 and 376-382 New South Head Road, Double Bay (the Contract).
On 4 July 2023, the Contractor went into liquidation. The Developer subsequently commenced these proceedings, seeking leave pursuant to sections 4 and 5 of the TPC Act, to recover loss and damages from the Contractor’s Insurer who (the Developer argued) would have been responsible for indemnifying the Contractor for the following six categories of claims totalling over $4,500,000:
In order for the Developer to be granted leave, the Developer needed to establish three elements (at [54]):
Notably, William J remarked and foreshadowed at [56] and [57] that:
“As the Plaintiff submitted, the standard of an arguable case is “fairly low”… one case circumstance in which the Court may conclude that there is no arguable case of insured liability is where the relevant insurance policy is a claims made policy, and there is no evidence of a relevant claim having been made against the insured during the period of the policy. Any such determination simply relies on the proper characterisation of written correspondence”
“Even if each of the three elements is established, there is a residual discretion to refuse leave rather than to permit the applicant to commence an action against the insurer who the applicant otherwise has no right to sue”.
With respect to each of the three elements, both the Developer and the Contractor’s Insurer’s positions were as follows:
However, the Contractor’s Insurer argued that the Developer had failed to demonstrate that the Contractor would have been entitled to indemnity under the policies in relation to any of the six categories of claims alleged for the following reasons (at [66]):
The Court examined the Developer’s six categories of claims and, in each instance, found that there was no arguable case that the Contractor would have been entitled to be indemnified by its Insurer and that a reasonable businessperson would not have interpreted the correspondence from the Developer as a ‘written demand for civil compensation or civil damages or non-monetary civil relief’ as required by policies.
In arriving at these conclusions, the following key findings were made:
For Insurers, this decision reinforces the importance of precise policy drafting and careful claims management. The Court’s approach underlines that coverage will only be triggered where the claimant can demonstrate that a valid “Claim” — as defined in the policy — was made within the policy period, meets the insuring clause’s scope (such as being connected to “Professional Services”), and results in a covered “Loss.” Correspondence that merely complains, requests rectification, or foreshadows potential demands is unlikely to cross that bar.
For insureds, and third‑party claimants, this case is a highlights that success under the TPC Act is not simply about proving underlying liability but is dependent on satisfying the policy’s specific preconditions for indemnity. Timely, clear and unequivocal demands that fit within policy definitions are essential, and maintaining documentation that links those demands to matter(s) capable of giving rise to an indemnifiable claim. Without this, even compelling substantive claims against an insolvent insured may result in leave to make a third party claim being denied.
If you would like further information or have any queries regarding other matters, please do not hesitate to contact: