By Sarah Pick, Partner
On 22 May 2025, the Australian Energy Market Commission (AEMC) released its Final Rule Determination (Final Determination) and the National Electricity Amendment (Improving the NEM access standards – Package 1) Rule 2025 (Final Rule) (Rule Change).
The Rule Change is a result of the rule change request from the Australian Energy Market Operator (AEMO) on 4 April 2024 to improve the technical requirements for connection[1] to the National Electricity Market (NEM). The technical requirements for connections are set out in Chapter 5 of the National Electricity Rules (NER) and are known as ‘access standards’. The AEMC initiated the rule change request under the ‘fast track process’ and consequently did not issue a consultation paper and instead published a draft rule determination (Draft Determination) and draft rule (Draft Rule) on 5 December 2024.
The Final Determination provides that the AEMC made a more preferable Final Rule that largely maintains the Draft Rule but also makes several additional clarifications in response to the 23 submissions received in Draft Rule and Draft Determination.
The key change that the Final Rule implements is that the access standards set out in Chapter 5 of the NER will now be applied by plant type as opposed to being applied based on the registration category of the operator of the plant (which is the current approach). In order to facilitate these changes, a number of new definitions have been included in the NER.
The purpose of this article is to set out:
In addition to changing the application of the access standards, the Rule Change also makes several technical amendments to the access standards. This article does not discuss these changes.
The Rule Change will commence on 21 August 2025, so it’s important to start thinking about how it may impact current, future or proposed connections.
Schedule 5.2’s current title is ‘Conditions for Connection of Generators and Integrated Resource Providers’ and it applies to registered Generators and registered Integrated Resource Providers.[2]
The new title for Schedule 5.2 will be ‘Technical connection requirements for generating systems, integrated resource systems and synchronous condensers’ and it will apply to Schedule 5.2 Participants in respect of schedule 5.2 plant.[3]
Schedule 5.2 plant[4]is:
A person is a Schedule 5.2 Participant in respect of schedule 5.2 plant if that person is one of the following:[5]
Consequently, after the commencement of the Final Rule (subject to the transitional provisions), Schedule 5.2 will apply to Schedule 5.2 Participants in respect of schedule 5.2 plant.
Schedule 5.3’s current title is ‘Conditions for Connection of Customers’ and it applies to Market Customers in respect of its market connection points, Non-Registered Customers in respect of its connection to a network and a Distribution Network Service Provider in respect of its distribution network.[13]
The new title for Schedule 5.3 will be ‘Technical connection requirements for loads’ and it will apply to Schedule 5.3 Participants in respect of schedule 5.3 plant.[14]
Schedule 5.3 plant[15]is plant that consumes electricity from a network:
A person is a Schedule 5.3 Participant[16] in respect of schedule 5.3 plant if that person is one of the following:[17]
Consequently, after the commencement of the Final Rule (subject to the transitional provisions), Schedule 5.3 will apply to Schedule 5.3 Participants in respect of schedule 5.3 plant.
Schedule 5.3a’s current title is ‘Conditions for Connection of Market Network Services’ and it applies to Market Network Service Providers who connect to either a transmission network or a distribution network.[22]
The new title for Schedule 5.3 will be ‘Technical connection requirements for high voltage direct current networks’ and it will apply to Schedule 5.3a Participants in respect of schedule 5.3a plant. [23]
Schedule 5.3a plant[24]is a system comprising high voltage direct current technology with a power transfer capability of 5MW or more, used to transfer electricity to, from or between one or more alternating current networks (or parts of any alternating current network) of a Network Service Provider).
A person is a Schedule 5.3a Participant[25] in respect of schedule 5.3a plant if that person is:[26]
Consequently, after the commencement of the Final Rule (subject to the transitional provisions), Schedule 5.3a will apply to Schedule 5.3a Participants in respect of schedule 5.3a plant.
The Final Rule sets out transitional provisions that set out whether a Connection Applicant will need to ensure its plant complies with the access standards under the Final Rule (New Access Standards) or the access standards currently set out in the Chapter 5 of the NER (Old Access Standards).
The below diagram sets out how to determine whether the New Access Standards or the Old Access Standards will apply to a new connection or a connection alteration.

As indicated in the above flow chart, there are some circumstances where a Connection Applicant may give the Network Service Provider notice that it wishes to apply some or all of the New Access Standards to the plant it is proposing to connect.
Where the Connection Applicant advises that it wishes to apply all of the New Access Standards to the plant it is proposing to connect:
Where the Connection Applicant advises that it wishes to apply some of the New Access Standards and some of the Old Access Standards (Mixed Access Standards), rule 11.186.4 of the Final Rule sets out the process that the Network Service Provider and AEMO will follow to determine whether the proposed Mixed Access Standards are accepted or rejected.
For projects that have already commenced the connection process or are looking to commence the connection process prior to the commencement of the Final Rule, it is important that consideration is given to the impact that the Final Rule will have on the access standards for the project.
If you need further help considering the implications of the Final Rule and how it may impact a connection project, please reach out for assistance.
[1] Unless the context otherwise requires words in italics have the meaning given to that term in the National Electricity Rules (version 227) or the Final Rule (as applicable).
[2] Schedule 5.2 of National Electricity Rules (version 227).
[3] Schedule 5.2 of Final Rule.
[4] Rule S5.2.1(a) of Final Rule.
[5] Table 3.1 on page 13 of Final Determination.
[6] Rule S5.2.1(b)(1)(i) of Final Rule.
[7] Rule S5.2.1(b)(1)(ii) of Final Rule.
[8] Rule S5.2.1(b)(2)(i) of Final Rule.
[9] Rule S5.2.1(b)(2)(ii) of Final Rule.
[10] Rule S5.2.1(b)(3)(i) of Final Rule.
[11] Rule S5.2.1(b)(3)(ii) of Final Rule.
[12] Rule S5.2.1(b)(4) of Final Rule.
[13] Schedule 5.3 of National Electricity Rules (version 227).
[14] Schedule 5.3 of Final Rule.
[15] Rule S5.3.1a(a) of Final Rule.
[16] Rule S5.3.1a(a1) of Final Rule.
[17] Table 3.1 on page 14 of Final Determination.
[18] Rule S5.3.1a(a1)(1)(i) of Final Rule.
[19] Rule S5.3.1a(a1)(1)(ii) of Final Rule.
[20]Rule S5.3.1a(a1)(1)(iii) of Final Rule.
[21] Rule S5.3.1a(a1)(2) of Final Rule.
[22] Schedule 5.3a of Final Rule.
[23] Schedule 5.3a of National Electricity Rules (version 227).
[24] Chapter 10 of Final Rule.
[25] Rule S5.3a.1a(b) of Final Rule.
[26] Table 3.1 on page 14 of Final Determination.
[27] Rule S5.3a.1a(b)(1) of Final Rule.
[28] Rule S5.3a.1a(b)(2)(i) of Final Rule.
[29] Rule S5.3a.1a(b)(2)(ii) of Final Rule.
[30] Rule S5.3a.1a(b)(2)(i) of Final Rule.
[31] Rule S5.3a.1a(b)(2)(ii) of Final Rule.
If you would like further information or have any queries regarding other matters, please do not hesitate to contact: