By Aaron Gadiel, Partner
A new decision from the Court of Appeal has re-affirmed some key legal points about development control plans (DCPs).
DCPs are among the most frequently relied upon — and most frequently misunderstood — instruments in development application assessment.
Local council officers often treat DCP standards as though they carry the same binding force as an environmental planning instrument (EPI). They do not.
This month’s NSW Court of Appeal decision in Conway v Leeroy Property Investments Pty Ltd [2026] NSWCA 123 is a helpful reminder as to the status of DCPs.
This article gives an overview of the legal framework governing the status of DCPs — and the circumstances in which their provisions must give way. The article deals with Conway, but also deals with legal points not addressed by Conway. This article is not a replacement for legal advice.
Section 3.42(1) of the Environmental Planning and Assessment Act 1979 (the EP&A Act) describes the principal purpose of a DCP as providing guidance — to both applicants and consent authorities — on:
Critically, section 3.42(1) expressly says that provisions of a DCP made for this purpose are ‘not statutory requirements’. They guide, rather than bind.
Under section 4.15(1)(a)(iii), a consent authority must ‘take into consideration’ the relevant provisions of a relevant DCP when assessing a development application.
This does not mean that a DCP must be rigidly followed (Conway at [40]).
The NSW Court of Appeal clarified the practical effect of this obligation in Warkworth Mining Limited v Bulga Milbrodale Progress Association Inc [2014] NSWCA 105 (at [213]-[215]).
At a minimum, a decision-maker must ask what the DCP provides — but is not obliged to refuse an application simply because a DCP standard is not met.
Instead, the decision-maker may need to consider why the standard should not apply, or whether non-compliance can be addressed through conditions of consent. Reasons advanced by an applicant for departing from a control must also be considered. Provided genuine consideration is given, a DCP standard may ultimately not be applied at all, if a proper merit case is made out on the facts.
Unlike draft EPIs, the EP&A Act does not expressly require a consent authority to consider a draft DCP.
Nevertheless, both the consent authority (and the Land and Environment Court in a merit appeal) may have regard to draft DCP as part of its consideration of the ‘public interest’ (a separate mandatory consideration in section 4.15(1)(e) of the EP&A Act): Carsens v Pittwater Council [1999] NSWLEC 249 at [25] and Pittwater Council v Mount [2000] NSWLEC 256 at [10].
For example, in Maxnoz Pty Ltd v Hurstville City Council (2006) 145 LGERA 373, the Court (at [20]) accepted that the council could consider an interim residential development code that had earlier existed as a draft DCP.
At times, a DCP has no effect at all. Section 3.43(5) of the EP&A Act is the key constraining provision.
A DCP provision has no effect to the extent it is:
(An EPI includes a local environmental plan (LEP) and a state environmental planning policy (SEPP).)
The Land and Environment Court has often applied this provision. Some examples:
It is also helpful to consider the Land and Environment Court’s application of a separate statutory inconsistency test that applies to concept development consents and detailed development applications. The test is similar to, and likely relevant to, the application of the inconsistency test between EPIs and DCPs.
In The Uniting Church in Australia Property Trust (NSW) v Parramatta City Council [2018] NSWLEC 158 at [44], the Chief Judge (Preston CJ) illustrated that inconsistency can cut both ways: a building that significantly undershoots an approved building envelope (for example, 10 storeys against an approved 15) can be just as inconsistent as one that exceeds it.
Speaking generally, we consider that (in light of this decision) DCP provisions that necessarily have the effect of materially preventing a development from reaching the planned height or intensity envisaged by an EPI would be inconsistent with that EPI and have no effect.
For some ‘edge’ cases there may be room for legal debate about whether a provision has no effect or should just be given little weight (in the light of a competing control in an EPI).
For example, section 177 of the State Environmental Planning Policy (Housing) 2021 (the Housing SEPP) sets out a landscaping consideration for development in ‘low and mid rise housing’ areas zoned R3 and R4. It says that development consent must not be granted for development for the purposes of residential flat buildings or shop top housing unless the consent authority has considered the Tree Canopy Guide for Low and Mid Rise Housing (2025).
The Tree Canopy Guide sets benchmarks for tree canopy at 15 per cent and 7 per cent (with some ‘enhanced’ numbers for larger sites).
Some DCP provisions impose a higher general standard for, say, deep soil (such as the Ku-ring-gai Development Control Plan which sets a 40 per cent or 50 per cent standard in control 1 of section 7A.6 ‘Deep Soil Landscaping’). When confronted with such an inconsistency a consent authority might conclude that this provision means that the DCP provision has no effect. Alternatively, the consent authority may decide that it does have effect, but gives it little weight in the light of the more-tailored Tree Canopy Guide that has been explicitly prepared in the light of the heights and floor space anticipated in the ‘low and mid rise housing’ areas.
Several SEPPs contain their own override mechanisms that limit the operation of DCP provisions under section 3.43(5) of the EP&A Act.
The most notable of these is section 2.10 of the State Environmental Planning Policy (Planning Systems) 2021. This provision says that DCPs do not apply to state significant development.
In another example, section 149 of the Housing SEPP says that a requirement, standard or control for residential apartment development in a DCP (where the development is subject to the Apartment Design Guide) has no effect in relation to:
In a further example, section 3.27 of the State Environmental Planning Policy (Transport and Infrastructure) 2021 contains a broad (although not exhaustive) override of DCP provisions for centre-based child care facilities.
In the recent decision of Palm Lake Works Pty Ltd v Tweed Shire Council [2025] NSWLEC 1847, the Court (at [78]-[79]) agreed with the submissions made by the developer (represented by Mills Oakley) that the provisions of the DCP prohibiting development within ecological buffer zones were fundamentally inconsistent and incompatible with the provisions of the State Environmental Planning Policy (Resilience and Hazards) 2021 (the Resilience and Hazards SEPP).
Sections 2.8, 2.10 and 2.11 of the Resilience and Hazards SEPP provide that development consent may be granted on land within areas mapped as ‘proximity area for coastal wetlands’, ‘coastal environment area’ and ‘coastal use area’, subject to consideration of the impacts of the proposed development on a number of matters, and satisfaction of further matters. In contrast, the DCP prohibited development within these areas in totality, and as a result the developer submitted that the DCP was inconsistent and incompatible with the SEPP and the DCP provisions had no effect. The Court accepted the application of the DCP in relation to prohibiting development within the mapped ecological buffers. The Court found that it was relevant to consider the environmental impact of the incursion of the proposed development into the buffer zones, but not to prohibit development if those impacts are acceptable, as per the relevant parts of the Resilience and Hazards SEPP.
Section 4.15(3A)(a) of the EP&A Act, provides that where a development complies with a DCP standard for a particular aspect of development, the consent authority cannot demand a more onerous standard for that same aspect.
Three decisions illustrate the Land and Environment Court’s application of this rule:
Where a development does not comply with a DCP standard, section 4.15(3A)(b) of the EP&A Act requires the consent authority to apply the provisions flexibly and allow reasonable alternative solutions that achieve the standard’s objects (Conway at [45] and [69]).
Bellenger v Randwick City Council [2017] NSWLEC 1 is the leading authority on how this works in practice:
The facts of Bellenger provide a useful illustration:
Section 4.15(3A)(c) of the EP&A Act confines a consent authority’s consideration of DCP controls to the subject development application, and not any other development applications.
This provision ‘contains’ the discretion of the consent authority: Hurley v Sutherland Shire Council [2016] NSWLEC 1630 at [60].
In 90 Croatia Properties Pty Ltd v Liverpool City Council [2021] NSWLEC 1177, the Court said (at [62]) that consent authorities:
This limitation does not only operate when consideration of past or future development applications would be ‘unreasonable’. The limitation on the scope of consideration applies more generally.
Understanding these limits is essential for applicants seeking to challenge an overly rigid application of DCP controls.
If you would like further information or have any queries regarding other matters, please do not hesitate to contact: