By Aaron Gadiel, Partner
The NSW Government’s Development Coordination Authority officially starts work on 1 July 2026.
Last Friday (19 June) the NSW Government published a suite of documents to give effect to the detailed legal arrangements. This comprised:
Mills Oakley published an article outlining key aspects of the broader planning system reforms on 17 November 2025. Mills Oakley also published an article on the commencement of the first round of the reforms on 22 December 2025. Additionally, Mills Oakley published an article on the commencement of the second round of the reforms on 10 March 2026.
This article highlights some key changes in the latest round of reforms which may be of interest to property developers and their consultants. It does not list all of the changes. This article is not a substitute for legal advice.
The ‘Development Coordination Authority’ will formally come into operation on 1 July 2026.
The first thing to appreciate is that this sounds like a new major institution, but, in truth, the Authority will simply be the Secretary of the Department of Planning, Housing and Infrastructure (DPHI) wearing a different hat. The staff doing the work of the Authority will merely be officers of the DPHI.
The Development Coordination Authority will take responsibility for issuing ‘general terms of approval’ in lieu of other NSW Government agencies when they are required for integrated development.
In brief terms — and notably for developers of urban property — general terms of approval are needed in the assessment of a development application when, to carry out the development, one of the following approvals would apply:
In the above circumstances, the Development Coordination Authority will issue the ‘general terms of approval’ rather than the individual agencies referred to above.
Once development consent is granted, there will still be a need to obtain the actual approval from the relevant agency. (There is no change to the existing requirement that the subsequent approval must then be granted, consistent with the development consent, if an application is made within three years after the grant of the development consent.)
Additionally:
From 1 July 2026 there will be a new expanded Chapter 4 (‘Concurrences and consultations’) in the State Environmental Planning Policy (Planning Systems) 2021 (Planning Systems SEPP) (replacing, in its entirety, the existing Chapter 4). Notably, for developers of urban property the Development Coordination Authority will take the place of TfNSW and related transport authorities in relation to the following matters:
The Development Coordination Authority has not been given any statutory role in the preparation and finalisation of ‘works authorisation deeds’ under the Roads Act 1993. These deeds are typically required by TfNSW before it will approve the carrying out of necessary work for a development on a classified road.
It is an open question as to whether this reform will be a change for the better. The reform might be seen as hollow if all that happens is that another layer is created between:
For example, it is likely that the Development Coordination Authority will not make decisions on some sensitive transport matters without some degree of consultation by it with TfNSW. If the Authority simply acts as a post box between the local council, the development applicant and TfNSW, the reform may have little benefit — and may, in fact, be negative.
The changes associated with the Development Coordination Authority do not generally apply to pending development applications that have been lodged before 1 July 2026.
Until now:
This changes from 1 July 2026.
Now, if an environmental planning instrument requires notification, consultation or the concurrence of a person (including a state government agency) before the grant of the original development consent, that same process of notification, consultation or concurrence must be repeated before either a ‘section 4.55(1A)’ or ‘section 4.55(2)’ modification can be approved.
This imposes a more onerous procedural burden on the approval of a ‘section 4.55(1A)’ modification application, but a lighter burden on a ‘section 4.55(2)’ modification.
The procedures outlined above do not apply to state significant development.
The Planning Systems SEPP will contain new provisions that prevent approval from being given to the modification application unless the consent authority has:
Until now there has been a statutory obligation — independent of anything in a gateway determination — for a planning authority to consult the DCCEEW before making or amending an environmental planning instrument.
This requirement will be removed on 1 July 2026.
However, a gateway determination — for a new or amended local environmental plan — may still require a planning authority to consult DCCEEW.
For a new or amended state environmental planning policy there will be no legal requirement for the DPHI to consult DCCEEW.
Interestingly, the legal challenge by Ku-ring-gai Council against the State Environmental Planning Policy (Housing) Amendment (Transport Oriented Development) 2024 was principally based on a breach of this existing legal requirement. After 1 July 2026, no similar legal challenge could be sustained against the NSW Government in the future.
Until now — for development that does not require a ‘bushfire safety authority’ from the Rural Fire Service — a consent authority has been unable to grant a development consent unless either one of the following three circumstances exist:
From 1 July 2026, this rule will be scrapped.
Instead, a consent authority will only be required to consider Planning for Bush Fire Protection (for development that does not require a ‘bushfire safety authority’ from the Rural Fire Service).
A new Division 3 (‘Bush fires’) in Part 4.2 (‘Concurrences and consultations’) of the Planning Systems SEPP now sets out a consultation requirement with the Development Coordination Authority.
This change does not apply to pending development applications that have been lodged before 1 July 2026.
Under the existing law, development consent can be (and routinely is) granted with conditions that require an aspect of the development to be carried out to the satisfaction of a person, such as a state government agency.
This power remains.
However, the new statutory scheme for the Development Coordination Authority expressly anticipates that conditions of development consent may require that an aspect of the development be carried out to the satisfaction of the Development Coordination Authority.
When such a condition is imposed — and the Development Coordination Authority is not satisfied — there will be a new ability to seek an internal review of that decision by the Authority under Division 8.2 of the EP&A Act.
This right is in addition to the existing right to appeal to the Land and Environment Court (when a local council or a third-party, such as the Development Coordination Authority, is not satisfied under a condition of development consent).
Under the existing law a development application is required to contain:
From 1 July 2026, this requirement will be expanded (in one respect) and narrowed (in another respect).
It will also be necessary to provide a list of the provisions of an act of parliament or an environmental planning instrument that require a consent authority to consult with a consultation body before granting development consent.
For state significant development, it will no longer be required to include in the list a concurrence requirement which is imposed by an environmental planning instrument — so long as that requirement is not expressed to apply to state significant development.
There will no longer be an automatic requirement to re-refer every amendment of a development application to a referral authority (whose concurrence or consultation is required, or from whom general terms of approval are needed).
A consent authority will have the power to decide not to refer the application if it considers that the amendment will not affect the assessment of the development undertaken by the referral authority.
The creation of the Development Coordination Authority is a real effort to remove some of the bureaucratic inefficiencies from development assessment in NSW.
However, if not well-managed, there is a risk that the Development Coordination Authority will become a layer between a development applicant and the real decision-maker somewhere in the bowels of government. Let’s hope that this is just misplaced pessimism.
If you would like further information or have any queries regarding other matters, please do not hesitate to contact: