Bring Your Own Power Supply: What’s New in Victoria’s Data Centre Action Plan

Victoria released its Sustainable Data Centre Action Plan on 22 September 2026, outlining expectations for new data centres across land use, energy, water and employment. The Plan will be supported by a new planning framework, including a dedicated data centre land use classification and new referral pathways for energy and water authorities.
October 26 2026

By Brandon Melton, Lawyer, Luke Westmore, Partner and Tony Rutherford, Partner

Victoria released its Sustainable Data Centre Action Plan on 22 September 2026. The Plan sets out the State’s expectations for new data centres across land use, energy, water and employment, with those expectations to be implemented through a new planning control framework, including a dedicated data centre land use and new referral pathways for energy and water authorities.

The policy backdrop is clear. The Australian Energy Market Operator (AEMO) forecasts that data centres’ share of electricity consumption in the National Electricity Market could increase from around 3% today to approximately 12-13% by 2035-36. Against this forecast growth, Victoria is seeking to link new data centre demand with new investment in generation, storage and network infrastructure, ensuring the costs and reliability impacts of that growth are not borne by other energy consumers.

Electricity Supply and Network Requirements:

The most significant aspect of the Action Plan is its adoption of what is effectively a “bring your own power supply” model for new data centre projects. Rather than treating data centres as ordinary electricity consumers, the Plan links the development of new large loads to the procurement of new energy supply and supporting infrastructure.

In practical terms, operators are expected to:

  • offset actual operational electricity consumption through investment in new renewable generation and storage;
  • fund connection and network augmentation costs attributable to their projects, including upstream augmentation works;
  • participate in demand flexibility services; and
  • design facilities to minimise energy losses and optimise operational efficiency

For new projects, power procurement is likely to become a critical component of the investment case rather than a matter addressed after key development decisions have been made. The ability to secure renewable generation, storage capacity and network access is increasingly likely to influence project feasibility, financing outcomes and overall investor appetite for large-scale data centre developments.

Victoria’s Data Centre Action Plan in the National Context:

Victoria’s Action Plan sits within a broader policy debate about how Australia should accommodate the rapid growth of the data centre sector. In its March 2026 policy outline, Expectations of Data Centres and AI Infrastructure Developers, the Commonwealth Government indicated that growth in data centre demand should be accompanied by investment in clean generation, storage and energy efficiency measures, together with participation in demand flexibility services.

National Cabinet agreed to develop mandatory national standards for data centre projects in August 2026, but views have since diverged on the role of conventional generation in powering the sector’s growth. Victoria has largely maintained the policy direction reflected in the Commonwealth’s original proposals, continuing to emphasise the role of renewable generation and storage in supporting new data centre demand. The Victorian requirements are intended to sit alongside the Commonwealth’s emerging national standards, with the result that both frameworks will be relevant to Victorian data centre projects.

Implications for Data Centre Projects in Victoria:

For data centre developers, the proposed reforms mean that energy procurement can no longer be treated as a downstream commercial exercise. The ability to secure renewable generation, storage capacity and network access is likely to influence site selection, approval pathways, connection costs and project viability. If time-based matching requirements are ultimately adopted under the Victorian framework, developers may need to look beyond traditional run-of-plant PPAs towards firmed renewable products, hybrid renewable and storage arrangements, and other contracting structures capable of delivering round-the-clock supply. Power purchase agreements entered into before the regulatory framework is settled should also address change-in-law risk, certificate arrangements and responsibility for any future firming obligations.

For renewable energy and storage developers, the reforms create a new category of customer with a regulatory incentive to contract for new capacity. Connection negotiations are also likely to evolve, with funded augmentations, prudential support and future cost allocation becoming increasingly important as policymakers seek to ensure that large new loads bear the costs they impose on the system. Although significant implementation detail remains to be settled, the direction of travel is clear: power procurement is becoming increasingly central to project feasibility, financing and investment decisions for large-scale data centre developments.

Our Projects and Energy Transition team advises clients across the energy sector on project development, energy procurement, network access and other energy regulatory matters. If you would like to discuss any of these issues, please contact a member of our team.